Project Overview & Scope
- Location: Pars Special Economic Energy Zone, Assaluyeh
- Scope of Work: Execution of Electrical, DCS Control Systems and Process Instrumentation
- Contract Model: Construction Contractor (C)
- Delivery Status: Completed
Technical Summary
The Sadaf Petrochemical project in Assaluyeh aimed at producing 136,000 tons/year of ESBR synthetic rubber. Rastak Pouya's scope encompassed MV/LV cabling, transformer and switchgear erection, installation of hazardous area instrumentation, and commissioning of the distributed control system (DCS) and ESD safety loops.